ASNR Resolutions

The 13th June 2006 Act lists the various categories of regulatory or individual resolutions issued by ASN, for instance:

  • regulatory resolutions of a technical nature for implementation of decrees or orders issued concerning nuclear safety and radiation protection;
  • basic nuclear installation (BNI) commissioning authorisation;
  • authorisations or approvals concerning the carriage of radioactive substances or medical facilities and equipment utilising ionising radiation.

53 texts

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0297 of 26 June 2012

ASN resolution 2012-DC-0297 of 26 June 2012 instructing the French atomic energy and alternative energies commission (CEA) to comply with requirements applicable to basic nuclear installation (BNI) 40 (Osiris) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0298 of 26 June 2012

ASN resolution 2012-DC-0298 of 26 June 2012 instructing the COMURHEX company to comply with additional requirements applicable to basic nuclear installation (BNI) called COMURHEX, located on the Tricastin site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0284 of 26 June 2012

ASN resolution 2012-DC-0284 of 26 June 2012 instructing Électricité de France – Société Anonyme (EDF-SA) to comply with additional requirements applicable to the Fessenheim NPP (Haut-Rhin département) in the light of the conclusions of the Complementary Safety Assessments (CSAs) for BNI 75

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0305 of 26 June 2012

ASN resolution 2012-DC-0305 of 26 June 2012 instructing the AREVA NC company to comply with additional requirements applicable to basic nuclear installation (BNI) called TU5, located on the Tricastin site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0299 of 26 June 2012

ASN resolution 2012-DC-0299 of 26 June 2012 instructing the EURODIF Production company to comply with additional requirements applicable to basic nuclear installation (BNI) called EURODIF, located on the Tricastin site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0300 of 26 June 2012

ASN resolution 2012-DC-0300 of 26 June 2012 instructing the FBFC company to comply with additional requirements applicable to basic nuclear installation (BNI) called FBFC, located on the Romans-sur-Isère site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0301 of 26 June 2012

ASN resolution 2012-DC-0301 of 26 June 2012 instructing the Société d’enrichissement du Tricastin (SET) to comply with additional requirements applicable to basic nuclear installation (BNI) called Georges Besse II, located on the Tricastin site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0302 of 26 June 2012

ASN resolution 2012-DC-0302 of 26 June 2012 instructing the AREVA NC company to comply with additional requirements applicable to basic nuclear installations (BNIs) 33 (UP2 400), 38 (STE2), 47 (ELAN IIB), 80 (HAO), 116 (UP3-A), 117 (UP2 800) and 118 (STE3), located on the La Hague site (Manche département) in the light of the conclusions of the Complementary Safety Assessments (CSAs)

Published on 01/03/2013

ASNR REGULATORY RESOLUTIONS

ASN resolution 2012-DC-0303 of 26 June 2012

ASN resolution 2012-DC-0303 of 26 June 2012 instructing the MELOX SA company to comply with additional requirements applicable to basic nuclear installation (BNI) 151, called MELOX, located on the Marcoule site (Gard département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 01/03/2013

ASNR STATUTORY RESOLUTIONS

ASN resolution 2012-DC-0304 of 26 June 2012

ASN resolution 2012-DC-0304 of 26 June 2012 instructing the SOCATRI company to comply with additional requirements applicable to basic nuclear installation (BNI) 138 called SOCATRI, located on the Tricastin site (Drôme département) in the light of the conclusions of the Complementary Safety Assessment (CSA)

Published on 03/03/2014

ASNR STATUTORY RESOLUTIONS

ASN Resolution no. 2011-DC-0213 of 5th May 2011

ASN Resolution no. 2011-DC-0213 of 5th May 2011 instructing EDF to carry out a complementary safety assessment on some of its basic nuclear installations in the light of the accident which has occurred at the Fukushima Daiichi nuclear power plant

Published on 16/01/2012

ASNR STATUTORY RESOLUTIONS

Resolution 2011-DC-0224 dated 5 May 2011 from ASN

Resolution 2011-DC-0224 dated 5 May 2011 from ASN requiring the Commission for Atomic Energy and alternative energies (CEA) to carry out an additional safety assessment of some of its base nuclear installations following the accident that occurred at the Fukushima Daiichi nuclear power plant

Published on 16/01/2012

ASNR STATUTORY RESOLUTIONS

Resolution 2011-DC-0220 dated 5 May 2011 from ASN

Resolution 2011-DC-0220 dated 5 May 2011 from ASN requiring FBFC to carry out an additional safety assessment of some of its base nuclear installations following the accident that occurred at the Fukushima Daiichi nuclear power plant

Published on 16/01/2012

ASNR STATUTORY RESOLUTIONS

Resolution 2011-DC-0218 dated 5 May 2011 from ASN

Resolution 2011-DC-0218 dated 5 May 2011 from ASN requiring EURODIF SA to carry out an additional safety assessment of some of its base nuclear installations following the accident that occurred at the Fukushima Daiichi nuclear power plant

Published on 16/01/2012

ASNR STATUTORY RESOLUTIONS

Resolution 2011-DC-0219 dated 5 May 2011 from ASN

Resolution 2011-DC-0219 dated 5 May 2011 from ASN requiring SOCATRI to carry out an additional safety assessment of some of its base nuclear installations following the accident that occurred at the Fukushima Daiichi nuclear power plant